EIR/HUAWEI – MOBILE BUILD SRAN MODERNISATION 4G/5G/DSS

Date 25/1/2022

Key Takeouts

DESIGN

  • Survey
  • Initial Design & Structural Survey
  • Detailed Design
  • Build Collaboration
  • Post Construction Documentation (ABDs, H&S, Handover Packs)

INSTALLATION & COMMISSIONING (including Decommissioning)

  • Numerous indoor/outdoor across 800/900/1800/2100 bands
  • Installation of antenna line Equipment, supporting structures, cable management, earthling, power
  • Swap and install new BTS
  • BTS integration including trouble shooting
  • Decommissioning and removal of existing BTS, feeder line, antennas, mounts
  • Installation of additional Huawei cabinets/racks to support base station, power or transmission equipment. Includes installation and testing of external alarm
  • Commissioning of a site is completed including script delivery at the local end, license activation, software loading and call testing using Huawei WDT system (Process through Wireless Development Tool).
  • Huawei Smart QC report submission using Integrated Service Delivery Platform (ISDP)
  • Provision of lifting equipment including cranes, MEWP, HIAB, cherry pickers, including traffic management

ACCEPTANCE

  • Provision of site acceptance documentation including post construction documentation